TD-100 CASE STUDY (Trenching in Long Houghton)
- Customer - J Hughes Construction
- Client - Taylor Woodrow
- Project - 2m deep x 1.2m wide sewage pipe trenching for housing development in Long Houghton.
- Excavator - Daewoo 220 set at 320 bar delivering 40 kW of power.
- Excavation Rates - 0.7 m3/hour.
- Rock - Whin Stone or Grey Wacky: Unified Compressive Strength -- MPa Cerchar Abrasivity Number -.--
- Pick Consumption - Approximately 15 per cubic metre
Comments - Tom March (Site Foreman)
"Could not make any headway with hydraulic hammer as the depth of the trench increased, actually getting somewhere with the Rockwheel. Two hydraulic hammers broke within a month and the tool was only lasting two hours."
This project was an example of the flexibility a contractor gains with the inclusion of a ROCKWHEEL into his fleet of equipment. The ability to be able to swap between a bucket, hydraulic hammer and ROCKWHEEL ensures most tasks can be performed without the need for specialist equipment.
|